Concrete pour is underway at the Baptist Health South Florida Proton Therapy site

Press releases may be edited for formatting or style | March 16, 2016
MIAMI, FLORIDA (PRWEB) MARCH 16, 2016 -- Gilbane Building Company, the nationally recognized leader in proton therapy construction, recently completed the massive concrete placement for the Baptist Health South Florida Proton Therapy project. The new proton therapy treatment facility is only one of a handful of proton therapy centers in the country and the first in South Florida.

The total placement area of 2,200 cubic yards was split into three individual placements spanning over three days, with the individual placements ranging from 500-900 cubic yards. Due to the protons radiation, building the treatment areas require shielding walls that contain the protons with high-density concrete, which the concrete mix is made up of two types of high-density limestone aggregate. The limestone aggregate was specifically used to meet the density requirements, but also to control the heat generated to not exceed the temperature requirements of the mass concrete placements, which was the other major characteristic affecting concrete placements.

All individual placements started at 1:00 am and completed by 9:00 am to not exceed the ACI required 158 degree peak temperature per the Mass Concrete specifications. The concrete batching utilized ice and other means to cool the concrete temperature at batching, but the typically high ambient temperatures in Miami, FL caused concern for having any ability to consistently control the placement temperature during the day, resulting in the concrete placement window of 1:00 am to 9:00 am.
stats Advertisement
DOTmed text ad

Training and education based on your needs

Stay up to date with the latest training to fix, troubleshoot, and maintain your critical care devices. GE HealthCare offers multiple training formats to empower teams and expand knowledge, saving you time and money

stats
The majority of the MEP services and Proton Vendor conduits were embedded in the shielding walls, with the noted placement including over 15,000 LF of conduit. According to the Jason Martin, Senior Project Manager, the thickest wall to be poured is a 15’-6” feet shielding wall and it is 12’-0” feet high. The largest challenge was not only verifying all conduits are included in the placement, which required a significant Quality Assurance program and inspections, but that the layout is accurate and no conduits are damaged during placement.

“The completion of the complex pour of concrete for a facility of this magnitude is a major milestone for the project,” said Tim Hensey, vice president of Gilbane Building Company. “It is a highly technical and challenging process. Our experienced staff understands the unique issues of proton therapy facility construction and manages the process to ensure the project stays on schedule.”